Moor Park Health & Leisure Centre, Blackpool

Moor Park, Atrium Glazing Replacement

Replacing glazing at height requires more than specialist installation. It demands careful planning, safe access arrangements and coordination between multiple trades to ensure the work can be carried out safely and efficiently.

At Moor Park Health & Leisure Centre in Blackpool, Salt Town Contractors undertook an atrium glazing replacement project involving high-level glazing works, an internal crash deck, specialist crane lifting operations and associated internal making-good works.

The project required a coordinated approach to managing works both above and below the atrium, with particular consideration given to safe access, lifting arrangements and protection of the surrounding internal areas.

Project Overview

Salt Town Contractors was appointed to manage the replacement of glazing to the building’s high-level atrium skylight.

The scope involved coordinating specialist glazing contractors, crane operations and internal access arrangements to facilitate the removal and replacement of glazing at roof level.

An internal crash deck was incorporated into the works to provide protection beneath the glazing area, with associated decorating undertaken to make good the internal areas following the replacement works.

The Challenge

Replacing glazing within an elevated atrium presents a number of logistical and safety challenges, particularly where access is restricted and large glazing units must be handled at height.

At Moor Park, the works required careful coordination between the external crane operations and the internal working area.

The key consideration was establishing suitable access and protection arrangements to enable specialist glazing works to take place while managing the risks associated with lifting operations and overhead activity.

The surrounding internal finishes also needed to be considered throughout the project.

Our Atrium Glazing Replacement Solution

Salt Town Contractors coordinated a programme of specialist works to facilitate the replacement of the atrium glazing.

The works included:

  • Internal crash deck: Provision of a temporary protective working platform beneath the atrium glazing area.
  • Specialist crane operations: Coordination of crane lifting arrangements to support the handling and positioning of glazing units at roof level.
  • Specialist glazing installation: Working with glazing specialists to carry out the replacement of the high-level atrium glazing.
  • Access and safety arrangements: Planning and coordination of suitable working access and protective measures for activities at height.
  • Internal making good and decorating: Carrying out associated decorating works to make good the affected internal areas following the glazing replacement.

By bringing these elements together, STC provided a coordinated approach to a technically demanding glazing replacement project.

The Outcome

The project brought together specialist glazing expertise, crane lifting operations, internal protection measures and associated making-good works within one coordinated scope.

Alongside the replacement glazing, the internal decorating works addressed areas affected by the installation process, providing a complete approach that considered both the specialist glazing requirements and the surrounding internal finishes.

Moor Park demonstrates Salt Town Contractors’ capability to manage specialist building works involving multiple trades, complex access requirements and carefully planned lifting operations.

Whether delivering high-level glazing replacements, roofing works or wider building maintenance projects, STC focuses on practical solutions supported by experienced teams and effective project coordination.

Client.

Services.

Specialist Glazing, Work at Height Access, Crane Lifting Operations, Internal Making Good & Decorating