Hams Hall, Birmingham

Structural Steelwork Repairs & Cladding Replacement

 

Salt Town Contractors was appointed by Logistica FM to undertake a programme of structural steelwork repairs, corrosion treatment and cladding replacement at the Chubb National Distribution Centre in Hams Hall, Birmingham.

The project involved specialist works to the building’s high-level parapet structure, combining structural repairs, steelwork replacement and cladding reinstatement. With working areas approximately 45 metres above ground level, the project required carefully planned access arrangements, specialist equipment and coordinated site management.

 

The Project

The Chubb National Distribution Centre is a large commercial distribution facility located on Edison Road, Hams Hall.

Following the identification of corrosion affecting sections of the building’s parapet steelwork, Salt Town Contractors was engaged to coordinate a programme of remedial works designed to address deterioration and reinstate affected components of the building envelope.

The scope included the replacement of corroded structural steelwork, treatment of retained steel sections and removal and reinstatement of cladding to provide access to the affected areas.

Working at approximately 45 metres presented significant logistical and safety considerations, particularly when coordinating scaffolding, material handling and specialist trades within an operational distribution environment.

 

Scope of Works

Salt Town Contractors’ responsibilities encompassed the planning, coordination and delivery of several specialist work packages.

Structural Steelwork Repairs and Replacement

The structural repair programme included:

  • Removal and replacement of corroded Z-section roof purlins.
  • Replacement of affected parapet cladding rails and supporting steelwork.
  • Mechanical preparation and protective coating of existing steelwork affected by corrosion.
  • Installation of new galvanised steel purlins, sheeting rails and anti-sag wires.
  • Removal and replacement of a corroded steel parapet post.
  • Coordination of specialist steel fabrication and installation in accordance with structural engineering designs.

 

Cladding Removal and Reinstatement

To facilitate access to the structural elements, sections of the existing parapet cladding required temporary removal.

The works included the careful removal of external cladding sheets and parapet flashings, followed by reinstatement or replacement where necessary.

The cladding works were coordinated with the steelwork repairs to ensure affected structural components could be accessed and treated before the building envelope was reinstated.

Specialist Access and Working at Height

A key element of the project was establishing safe and practical access to the high-level working areas.

Access arrangements included:

  • Approximately 45 metres of scaffold working platform with a double-buttress access arrangement.
  • An additional 15-metre secondary access platform.
  • Mobile elevating work platforms (MEWPs), including specialist high-reach equipment.
  • Roof-level safety netting and demarcated working zones.
  • A Böcker Simply HD21 materials hoist for transporting equipment and materials to height.
  • Designated scaffold access, material storage and loading areas.

These arrangements supported the delivery of structural repairs and cladding works while maintaining controlled access to the work zones.

 

Project Challenges

Working Safely at 45 Metres

The height of the parapet structure was one of the principal challenges.

Working at this level required specialist access equipment, engineered scaffolding arrangements and detailed safety procedures to manage the risks associated with structural repairs and cladding removal.

Salt Town Contractors coordinated the access strategy, incorporating scaffold platforms, MEWPs, roof-level safety netting and designated demarcation zones.

Coordinating Multiple Specialist Trades

The project required close coordination between structural engineers, scaffolding specialists, steelwork contractors and cladding operatives.

The sequence of works was particularly important, as sections of cladding and supporting components needed to be removed before the structural repairs could proceed.

Salt Town Contractors managed the interface between these activities to establish a structured approach to the programme.

Working Within an Operational Distribution Facility

The building’s distribution environment introduced additional considerations for site access, deliveries, equipment storage and the movement of personnel.

Designated scaffold access routes, equipment storage areas and loading zones were incorporated into the site logistics plan.

The programme was coordinated with site management to manage the interface between construction activities and the facility’s operational requirements.

 

Our Approach

Salt Town Contractors adopted a coordinated approach to the project, bringing together structural engineering expertise, specialist access solutions and experienced installation teams.

The programme was organised into defined stages, beginning with site preparation and scaffold installation, followed by cladding removal, steelwork replacement and treatment, and subsequent cladding reinstatement.

Specialist contractors supported the delivery of individual work packages, with Salt Town Contractors overseeing the coordination of activities and site safety requirements.

Regular communication with the facilities management team formed an important part of the project, ensuring that access arrangements, deliveries and planned works were coordinated throughout the programme.

 

Project Outcome

The remedial works were designed to address corrosion affecting the distribution centre’s parapet structure through targeted steelwork replacement, protective treatment and cladding reinstatement.

By combining structural repairs with specialist high-level access and coordinated project management, the programme provided a comprehensive approach to maintaining the building’s structural components and external envelope.

The project demonstrates Salt Town Contractors’ capability to manage technically demanding industrial building repairs involving multiple specialist trades, complex access requirements and high-level construction activities.

 

Specialist Industrial Building Repairs

Salt Town Contractors provides specialist roofing, cladding, structural remedial works and planned maintenance services for commercial and industrial properties throughout the UK.

From high-level cladding replacement and corrosion treatment to complex building envelope refurbishment, our team works with facilities managers, property owners and commercial clients to deliver practical, professionally managed solutions.

Contact Salt Town Contractors to discuss structural repairs, industrial cladding refurbishment or specialist working-at-height requirements for your commercial property.

Client.

Logistica FM

Services.

Structural Steelwork & Cladding Repairs

Share.